No erosion control was done in 2019 due to continuous record high water flows, which prevented any contractor work on the three moderate erosion sites selected for this year. (see some flooding in this report).
These three sites are incorporated into 2020 plans for five additional sites to be worked on, plus a re-evaluation of site 60 work which was destroyed by the historic high flow in that section.
Ongoing Erosion Control Projects
January 2020 update
In 2019 Syers Dam was removed (see article for more details).
No erosion control was done in 2019 due to continuous record high water flows, which prevented any contractor work on the three moderate erosion sites selected for this year. (see some flooding in this report).
These three sites are incorporated into 2020 plans for five additional sites to be worked on, plus a re-evaluation of site 60 work which was destroyed by the historic high flow in that section.
View the Little Manistee Eroding Stream Bank Assessment
IN PROGRESS
Site # 37/38
Level: Severe
Status: done by Jim S
Notice/Acceptance: 10-2015
Evaluation:
Permit:
Work start-complete: 10/15
Site # 20
Level: Severe
Status: Private
Notice/Acceptance:
Evaluation: 10/15 & 1/18 no reply as yet
Permit:
Work start-complete:
Site # 42
Level: Severe
Status: Private
Notice/Acceptance: 10/15 & 12/17
Evaluation: $1500
Permit: pending
Work start-complete:
NFS All 29 sites
Level:
Status: NFS
Notice/Acceptance: 2/16 & 1/17 & 1/18 no response from NFS
Evaluation:
Permit:
Work start-complete:
Sites # 1/2/12/14/15/18
Level: Moderate
Status: State
Notice/Acceptance: 9/16 – 9/16
Evaluation: 9/16
Permit: pending
Work start-complete:
ON HOLD
Sites # 19/31/32/34/35/39/48/51
Level: Moderate
Status: Private
on hold to do 2019?
COMPLETE
Sites # 10/13/16 – complete
Level: Severe
Status: State
Notice/Acceptance: 10/15 to CRA
Evaluation: $2400,3500,1000
Permit: 8/16
Work start-complete: 9/16 – 10/16
Sites # 36/37 – complete
Level: Severe
Status: State
Notice/Acceptance: 10/15 to CRA
Evaluation: $250,250
Permit: 8/16
Work start-complete: 12/16 – 4/17
Sites # 21/22/23/24/25/26
Level: Moderate/Minimum
Status: private
Notice/Acceptance: 10/15- 10/15
Evaluation: 10/15
Permit: 8/16
Work start-complete: done 9/16 on 22/23 & done 21 9/17